QUALITY / FAI
FAI proves the first part against the drawing—not the whole process.
A first article inspection records actual feature results for the first production-representative part. It is useful only when the drawing revision, datum scheme, measurement method and sample condition are defined.
ABERY engineering note
Updated November 20, 2026
FAI is a measurement record. It does not by itself prove capability, assembly, appearance or long-term process stability.
QUICK ANSWER
Use a ballooned drawing or approved inspection plan to identify every required feature, measure with the specified fixture and method, record actual values and pass/fail, resolve nonconformances, and sign the report against the exact part and drawing revision.
1. Define the FAI scope.
The buyer and supplier should agree whether FAI covers all dimensions, only critical-to-quality features or an assembly-level requirement. The drawing revision and acceptance standard must be the same for both parties.
For a molded part, identify whether the dimensions are measured after a settling period, after moisture conditioning or in an assembly fixture.
- Part number and drawing revision.
- Critical and functional features.
- Datum and fixture method.
- Sample condition and timing.
- Appearance and functional checks.
- Report format and approval signature.
2. Make the measurement plan auditable.
A ballooned drawing, feature list or CMM program should link each requirement to a result. The report should show nominal, tolerance, actual value, measurement tool and pass/fail.
When a feature cannot be measured directly, define an equivalent method and obtain approval. A value without the measurement method is difficult to defend.
| Dimension | Nominal, tolerance, actual and pass/fail. |
|---|---|
| Tool | CMM, gauge, projector or other method. |
| Fixture | Datum, restraint and sample condition. |
| Environment | Temperature and settling where relevant. |
| Appearance | Lighting, viewing area and reference sample. |
| Nonconformance | Deviation, disposition and corrective action. |
3. Review FAI with the process record.
A part can pass a dimensional report and still be unsuitable for production if the process is unstable, the cavity is unidentified or the sample was hand-selected. Link the FAI to the process sheet and trial condition.
For multi-cavity molds, identify the cavity and decide whether each cavity needs a representative FAI or a defined sampling plan.
Keep the revision trace.
An FAI report without the drawing, mold and process revision is not a durable acceptance record.
Review T1 validation4. What to request from the supplier.
Request the report in a usable format, not only a scanned summary. Include the feature list, actual values, nonconformances, disposition and approval. If PPAP is required, define how FAI fits the package.
A buyer should also keep the approved sample and measurement record for future production comparison.
- Drawing and revision used.
- Feature-by-feature results.
- CMM or gauge records.
- Appearance approval.
- Nonconformance and corrective action.
- Approval signature and date.
- Linked process sheet and sample ID.
Questions buyers ask before approving this scope.
What is the difference between FAI and T1?
Does FAI need to cover every cavity?
Can a supplier self-approve FAI?
What should I do with a failed feature?
Need a project-specific answer?
Send the part, material, volume and stage. We will identify what can be confirmed before quotation or tooling.
Send the projectContinue the engineering review.
Keep the scope comparable.
The linked guides are written to support a project-specific supplier and tooling review.
PROJECT INTAKE / FAI REVIEW
Define the measurement record before the first article.
Send the drawing, critical features and quality requirement. We can identify the FAI and T1 evidence needed for approval.
Tell us where the project is now.
Send the files and context you have. Missing information can be confirmed during review.
Business inquiries only. For large files, include a secure Google Drive, Dropbox, OneDrive or WeTransfer link, or email tonney@a-mold.com after submitting.